image description
The glass for the media center has been installed. There is just a little more work needed there.
image description
A mocked up classroom.
image description
image description
A large staircase inside of the main entrance has been started.
image description
image description
Sidewalks have been laid.
image description
image description
The electrical room.
image description
Hallway tiles.
image description
The tiles in the girl's locker room.
image description
image description
image description
The stage in the auditorium.
image description
image description
image description
image description
One of two green roofs. Eventually they will host an array of plants, which will soak up rain water.
image description
image description
image description
image description
The north parking lot was built.
image description

Taconic Construction: Progress Aided by Mild Fall

By Andy McKeeveriBerkshires Staff
Print Story | Email Story

The gym ceiling is being painted.
PITTSFIELD, Mass. — A mild autumn has helped move along outside work at the new Taconic High School.
 
As December sets in, concrete is still being poured. The mild weather has allowed workers to put sidewalks all around the school.
 
A parking lot in the north and roads in and out have all received the first layer of blacktopping. If the weather hadn't been as mild, that outside work would have waited until the spring.
 
Inside, the building is already prepared for the winter. Construction managers had a schedule calling for the building to be buttoned up in November, and heating pumped in to keep the building warm for finishing work throughout. Both of those targets have been hit.
 
By the end of October, the building was 62.8 percent complete and workers have been knocking out around 4 percent of the project per month. The work pace has been hitting the milestones on time, with an expected completion by the end of June. After that, furniture and equipment will be moved in to prepare the classrooms for the school year.
 
In October, the number of workers on site peaked at 178. Now, there are about 162 workers of all trades there. The $120.8 million project has been under construction for about a year and a half. And in many areas now, it is starting to look like a school.
 
The girl's locker room has maybe had the most noticeable change in recent months. Tiles have been placed on the wall throughout and walls have been painted. The locker room is on the second floor. Workers have started on the upper floors and moving down. The boy's locker room is a floor below and hasn't had tiling yet.
 
But on the second floor on the westernmost side of the building, tiling has been installed along the hallway walls, about three-quarters of the way up. Painters, meanwhile, are inside the classrooms putting the first few coats on.
 
The gymnasium's roof is now getting painted as well. The gym floor, however, won't be installed for a while so the wide open space is being used for storing material. 
 
The auditorium's stage has been poured. There is still work to be done near the roof, such as hanging the curtain, so the floor remains dirt and flat. Once that work toward the roof is complete, the ground will be dug down and sloped and concrete poured. The stage too will have a wood floor, which is expected to be installed this spring.
 
Workers have also begun to build a large staircase, which takes visitors from the main entrance to the media center and classrooms on the upper floors. The media center, which may be the most visually appealing part of the exterior with large pieces of glass spanning up a slanted room allowing significant natural light in, has a bit more framing work to go.
 
The easternmost side, which houses the shops on the first floor and classrooms on the upper floors, isn't as far along. But, just a few months ago the classrooms upstairs were merely framed out. Now, walls have gone up and painting has begun. 
 
The building is still being powered by generators but those will soon be replaced with the building's permanent power. 
 
iBerkshires has been following the construction since the beginning. Below is a slideshow from each visit. The slideshow is in chronological order since the start of construction.


Tags: Taconic school project,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

MassDOT Project Will Affect Traffic Near BMC

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass. — Prepare for traffic impacts around Berkshire Medical Center through May for a state Department of Transportation project to improve situations and intersections on North Street and First Street.

Because of this, traffic will be reduced to one lane of travel on First Street (U.S. Route 7) and North Street between Burbank Street and Abbott Street from 7 a.m. to 4 p.m., Monday through Friday through at least May 6.

BMC and Medical Arts Complex parking areas remain open and detours may be in place at certain times. The city will provide additional updates on changes to traffic patterns in the area as construction progresses.

The project has been a few years in the making, with a public hearing dating back to 2021. It aims to increase safety for all modes of transportation and improve intersection operation.

It consists of intersection widening and signalization improvements at First and Tyler streets, the conversion of North Street between Tyler and Stoddard Avenue to serve one-way southbound traffic only, intersection improvements at Charles Street and North Street, intersection improvements at Springside Avenue and North Street, and the construction of a roundabout at the intersection of First Street, North Street, Stoddard Avenue, and the Berkshire Medical Center entrance.

Work also includes the construction of 5-foot bike lanes and 5-foot sidewalks with ADA-compliant curb ramps.  

Last year, the City Council approved multiple orders for the state project: five orders of takings for intersection and signal improvements at First Street and North Street. 

The total amount identified for permanent and temporary takings is $397,200, with $200,000 allocated by the council and the additional monies coming from carryover Chapter 90 funding. The state Transportation Improvement Plan is paying for the project and the city is responsible for 20 percent of the design cost and rights-of-way takings.

View Full Story

More Pittsfield Stories